NP, .. just trying to provide a reality check for folks in similar
situations. We have had a lot of problems trying to figure out how to
get things done with our generator system, and sometimes it seems
like the local municipalities are just trying to CY[T]A at YOUR expense.
We used to have a split-bus panel, and for 15 years I physically
pulled the meter every time the generator was required. Only last
year did we get a transfer switch installed, .. at a cost of almost
***$4K***. (*Plus* the generator.)
Reality & practicality, while maintaining a sane level of safety,
trumps ivory tower regulations every time.